Development Update – August 2025

  • A temporary dust fence is being installed along Kaihalulu East Drive for 18–24 months to protect the environment and the construction area
  • Irrigation mainline realignment between holes 10 & 18 on the Fazio golf course continues with completion by the end of August
  • Mauka Basin work begins 
  • Foundational work on RR3 phase 1 continues
  • Public access to hiking and biking trails will remain open throughout construction, with temporary access available via the Kahuku Trail

    Recent News

    Development Update August 2026

    Development Update August 2026

    Construction continues on all four building sites.
    Selective tree trimming on H2 and RR3 is paused until September 15 when the ‘ōpe’ape’a (Hawaiian hoary bat) pupping season concludes.
    Fencing around the mauka basins work is nearly complete.
    Ongoing monitoring and maintenance of shoreline restoration and native planting.

    read more
    Development Update July 2026

    Development Update July 2026

    Construction continues on all four building sitesand Kaihalulu East Drive. 
    Selective tree trimming on H2 and RR3 paused at the end of May and will resume after September 15, when the ‘ōpe’ape’a (Hawaiian hoary bat) pupping season concludes.
    Mauka basins work is nearly complete with the installation of fencing.
    Ongoing monitoring and maintenance of shoreline restoration and native planting.