Development Update – August 2025

  • A temporary dust fence is being installed along Kaihalulu East Drive for 18–24 months to protect the environment and the construction area
  • Irrigation mainline realignment between holes 10 & 18 on the Fazio golf course continues with completion by the end of August
  • Mauka Basin work begins 
  • Foundational work on RR3 phase 1 continues
  • Public access to hiking and biking trails will remain open throughout construction, with temporary access available via the Kahuku Trail

    Recent News

    Development Update March 2026

    Development Update March 2026

    Work continues at Kaihalulu East Drive with utilities being installed.
    Mauka drainage basins excavation continues as weather allows.
    Vertical construction at RR3 phase 1 to resume in February with a targeted completion in early 2027.
    Shoreline restoration and native planting are ongoing.

    read more
    Development Update February 2026

    Development Update February 2026

    Work continues at Kaihalulu East Drive with utilities being installed.
    Mauka drainage basins excavation continues as weather allows.
    Vertical construction at RR3 phase 1 to resume in February with a targeted completion in early 2027.
    Shoreline restoration and native planting are ongoing with 2,500 native plants installed in 2025.

    read more
    Development Update January 2026

    Development Update January 2026

    Work continues at Kaihalulu East Drive with utilities being installed.
    Mauka drainage basins excavation continues as weather allows.
    Vertical construction at RR3 phase 1 to resume in February with a targeted completion in early 2027.
    Shoreline restoration and native planting are ongoing with 2,500 native plants installed in 2025.

    read more