Development Update – August 2025
- A temporary dust fence is being installed along Kaihalulu East Drive for 18–24 months to protect the environment and the construction area
- Irrigation mainline realignment between holes 10 & 18 on the Fazio golf course continues with completion by the end of August
- Mauka Basin work begins
- Foundational work on RR3 phase 1 continues
- Public access to hiking and biking trails will remain open throughout construction, with temporary access available via the Kahuku Trail
-
Recent News
Driving Positive Change: Areté Collective Supports Turtle Bay Foundation Golf Tournament
150 golfers from vendors, businesses and community partners teed off for a good cause at the 12th Annual Turtle Bay Foundation Golf Tournament, held at Turtle Bay’s Arnold Palmer Golf Course.
Development Update November 2025
Work continues at Kaihalulu East Drive, mauka drainage basins, and vertical construction at RR3 phase 1. Shoreline restoration and native planting are ongoing
Development Update October 2025
A temporary dust fence is being installed along Kaihalulu East Drive for 18–24 months to protect the environment and the construction area. Irrigation mainline realignment between holes 10 & 18 on the Fazio golf course continues with completion by the end of August. Mauka Basin work begins. Foundational work on RR3 phase 1 continues. Public access to hiking and biking trails will remain open throughout construction, with temporary access available via the Kahuku Trail