Recent News
Development Update June 2026
Construction continues, primarily focused on pads 3 and 4 of RR3 and Kaihalulu East Drive.
Selective tree trimming on H2 and RR3 paused at the end of May and will resume after September 15, when the ‘ōpe’ape’a (Hawaiian hoary bat) pupping season concludes.
Mauka basins work is nearly complete.
Ongoing monitoring and maintenance of shoreline restoration and native planting.
Meet Nordic PCL, the Team Building The North Shore Club
Nordic PCL has been appointed as general contractor for The North Shore Club and is now responsible for managing all aspects of construction for the project. The transition has been seamless, and Nordic is already on-site actively advancing progress on the first phase...
Development Update May 2026
Work continues at Kaihalulu East Drive with utilities being installed.
Most of the grading work on the mauka drainage basins has been completed.
Selective tree trimming on H2 (next to Ocean Villas) continues to remove hazardous ironwood vegetation.
A monitoring survey was recently completed by our biologist to assess habitats and species across Areté’s property.
Nordic PCL resumed vertical construction at RR3 phase 1 with a targeted completion in early 2027.
Ongoing monitoring and maintenance of shoreline restoration and native planting.
Continuing removal of invasive ironwood trees and mowing of undergrowth on RR3.
Development Update April 2026
Work continues at Kaihalulu East Drive with utilities being installed.
Most of the grading work on the mauka drainage basins has been completed.
Vertical construction at RR3 phase 1 to resume in April with a targeted completion in early 2027.
Phase 1 of shoreline restoration and native planting is complete with ongoing monitoring and maintenance in effect.
A huge mahalo to our golf maintenance team and Goodfellow Brothers (GBI) for clearing culverts and drainage pipes ahead of time to prevent major flooding.
Development Update March 2026
Work continues at Kaihalulu East Drive with utilities being installed.
Mauka drainage basins excavation continues as weather allows.
Vertical construction at RR3 phase 1 to resume in April with a targeted completion in early 2027.
Shoreline restoration and native planting are ongoing.
Development Update February 2026
Work continues at Kaihalulu East Drive with utilities being installed.
Mauka drainage basins excavation continues as weather allows.
Vertical construction at RR3 phase 1 to resume in February with a targeted completion in early 2027.
Shoreline restoration and native planting are ongoing with 2,500 native plants installed in 2025.
Contact Us to be the First to Receive Community Updates.


