honoring the past, preserving the future
In April 2024, Areté Collective acquired 60 acres on O’ahu’s North Shore to develop a low-rise resort residential community. The first phase will include 20 units in four buildings, with completion expected by 2027, followed by additional phases totaling 100 units.
Our Commitment to Sustainability + Stewardship
Areté Collective is deeply committed to being good stewards, incorporating sustainability and resource conservation throughout the project, and protecting native and endangered plants and wildlife.
Areté Collective is preserving 70% of the current site as open space, exceeding environmental requirements, and partnering with experts to restore native plants, protect endangered species, and rehabilitate the shoreline.
Recent News
Development Update May 2026
Work continues at Kaihalulu East Drive with utilities being installed.
Most of the grading work on the mauka drainage basins has been completed.
Selective tree trimming on H2 (next to Ocean Villas) continues to remove hazardous ironwood vegetation.
A monitoring survey was recently completed by our biologist to assess habitats and species across Areté’s property.
Nordic PCL resumed vertical construction at RR3 phase 1 with a targeted completion in early 2027.
Ongoing monitoring and maintenance of shoreline restoration and native planting.
Continuing removal of invasive ironwood trees and mowing of undergrowth on RR3.
Development Update April 2026
Work continues at Kaihalulu East Drive with utilities being installed.
Most of the grading work on the mauka drainage basins has been completed.
Vertical construction at RR3 phase 1 to resume in April with a targeted completion in early 2027.
Phase 1 of shoreline restoration and native planting is complete with ongoing monitoring and maintenance in effect.
A huge mahalo to our golf maintenance team and Goodfellow Brothers (GBI) for clearing culverts and drainage pipes ahead of time to prevent major flooding.
Development Update March 2026
Work continues at Kaihalulu East Drive with utilities being installed.
Mauka drainage basins excavation continues as weather allows.
Vertical construction at RR3 phase 1 to resume in April with a targeted completion in early 2027.
Shoreline restoration and native planting are ongoing.
Development Update February 2026
Work continues at Kaihalulu East Drive with utilities being installed.
Mauka drainage basins excavation continues as weather allows.
Vertical construction at RR3 phase 1 to resume in February with a targeted completion in early 2027.
Shoreline restoration and native planting are ongoing with 2,500 native plants installed in 2025.
Contact Us
Fill out the form to receive updates on future job opportunities, environmental updates, development progress, and more.

