Development Update – June 2026

    • Construction continues, primarily focused on pads 3 and 4 of RR3 and Kaihalulu East Drive.Most of the grading work on the mauka drainage basins has been completed.
    • Selective tree trimming on H2 and RR3 paused at the end of May and will resume after September 15, when the ‘ōpe’ape’a (Hawaiian hoary bat) pupping season concludes.
    • Mauka basins work is nearly complete.
    • Ongoing monitoring and maintenance of shoreline restoration and native planting.

Recent News

Development Update September 2026

Development Update September 2026

Construction continues on all four building sites.
Selective tree trimming on H2 and RR3 is paused until September 15 when the ‘ōpe’ape’a (Hawaiian hoary bat) pupping season concludes.
Fencing around the mauka basins work is nearly complete.
Ongoing monitoring and maintenance of shoreline restoration and native planting.

read more