Development Update – January 2026

  • Work continues at Kaihalulu East Drive with utilities being installed.
  • Mauka drainage basins excavation continues as weather allows.
  • Vertical construction at RR3 phase 1 to resume in February with a targeted completion in early 2027.
  • Shoreline restoration and native planting are ongoing with 2,500 native plants installed in 2025.

Recent News

Development Update September 2026

Development Update September 2026

Construction continues on all four building sites.
Selective tree trimming on H2 and RR3 is paused until September 15 when the ‘ōpe’ape’a (Hawaiian hoary bat) pupping season concludes.
Fencing around the mauka basins work is nearly complete.
Ongoing monitoring and maintenance of shoreline restoration and native planting.

read more