Development Update – April 2026

    • Work continues at Kaihalulu East Drive with utilities being installed.
    • Most of the grading work on the mauka drainage basins has been completed.
    • Vertical construction at RR3 phase 1 to resume in April with a targeted completion in early 2027.
    • Phase 1 of shoreline restoration and native planting is complete with ongoing monitoring and maintenance in effect.
    • A huge mahalo to our golf maintenance team and Goodfellow Brothers (GBI) for clearing culverts and drainage pipes ahead of time to prevent major flooding.

Recent News

Development Update November 2026

Development Update November 2026

Construction continues on all four building sites.
Fencing around the mauka basins is ongoing.
Ongoing monitoring and maintenance of shoreline restoration and native planting.

read more
Development Update October 2026

Development Update October 2026

Construction continues on all four building sites.
Fencing around the mauka basins is ongoing.
Ongoing monitoring and maintenance of shoreline restoration and native planting.

read more