Development Update – December 2025
- Fazio Golf irrigation work is complete
- Work continues at Kaihalulu East Drive, mauka drainage basins, and vertical construction at RR3 phase 1
- Shoreline restoration and native planting are ongoing
- November marks the beginning of the albatross breeding and nesting season in Hawaii. In November, albatross arrive at court and nest, lay eggs in December, and the chicks typically fledge in July or August. Please be sure to exercise caution around the property and golf course during this time as cart paths have been adjusted accordingly to the albatross nesting patterns.
- A special mahalo to the North Shore Community Land Trust for their efforts to restore the area as a breeding ground for albatross, and for their collaboration with the Hawaii Marine Animal Response to monitor and protect albatross while they’re on land.
- We are reminding our contractors of the significance of this time and continuing to implement our wildlife training for all our vendors and contractors who work on-site.
-
Recent News
Development Update June 2026
Construction continues, primarily focused on pads 3 and 4 of RR3 and Kaihalulu East Drive.
Selective tree trimming on H2 and RR3 paused at the end of May and will resume after September 15, when the ‘ōpe’ape’a (Hawaiian hoary bat) pupping season concludes.
Mauka basins work is nearly complete.
Ongoing monitoring and maintenance of shoreline restoration and native planting.
Meet Nordic PCL, the Team Building The North Shore Club
Nordic PCL has been appointed as general contractor for The North Shore Club and is now responsible for managing all...
Development Update May 2026
Work continues at Kaihalulu East Drive with utilities being installed.
Most of the grading work on the mauka drainage basins has been completed.
Selective tree trimming on H2 (next to Ocean Villas) continues to remove hazardous ironwood vegetation.
A monitoring survey was recently completed by our biologist to assess habitats and species across Areté’s property.
Nordic PCL resumed vertical construction at RR3 phase 1 with a targeted completion in early 2027.
Ongoing monitoring and maintenance of shoreline restoration and native planting.
Continuing removal of invasive ironwood trees and mowing of undergrowth on RR3.