Development Update – July 2025

  • Vertical construction of the four buildings on Phase 1 is ongoing.
  • Irrigation work on the mainline of the Fazio Golf Course near hole #10 is underway.
  • Beginning in mid-July, the Kaihalulu East Drive dust fence will be installed in preparation for constructing the public access road from Kuilima Drive to the new comfort station near ‘Ō‘io Stream.

    Recent News

    Development Update June 2026

    Development Update June 2026

    Construction continues, primarily focused on pads 3 and 4 of RR3 and Kaihalulu East Drive.
    Selective tree trimming on H2 and RR3 paused at the end of May and will resume after September 15, when the ‘ōpe’ape’a (Hawaiian hoary bat) pupping season concludes.
    Mauka basins work is nearly complete.
    Ongoing monitoring and maintenance of shoreline restoration and native planting.

    read more
    Development Update May 2026

    Development Update May 2026

    Work continues at Kaihalulu East Drive with utilities being installed.
    Most of the grading work on the mauka drainage basins has been completed.
    Selective tree trimming on H2 (next to Ocean Villas) continues to remove hazardous ironwood vegetation.
    A monitoring survey was recently completed by our biologist to assess habitats and species across Areté’s property.
    Nordic PCL resumed vertical construction at RR3 phase 1 with a targeted completion in early 2027.
    Ongoing monitoring and maintenance of shoreline restoration and native planting.
    Continuing removal of invasive ironwood trees and mowing of undergrowth on RR3.

    read more