Development Update – June 2025
-
Brett Hill is continuing foundational work on phase 1
-
Hui Kū Maoli Ola completed invasive tree removal on the property that began in April
-
Shoreline rehabilitation will continue to expand in July where ironwoods were recently removed
-
All ground-disturbing activity is monitored by a third-party, ASM Affiliates, a respected local firm with a long history of working at Turtle Bay
Recent News
Meet Nordic PCL, the Team Building The North Shore Club
Nordic PCL has been appointed as general contractor for The North Shore Club and is now responsible for managing all...
Development Update May 2026
Work continues at Kaihalulu East Drive with utilities being installed.
Most of the grading work on the mauka drainage basins has been completed.
Selective tree trimming on H2 (next to Ocean Villas) continues to remove hazardous ironwood vegetation.
A monitoring survey was recently completed by our biologist to assess habitats and species across Areté’s property.
Nordic PCL resumed vertical construction at RR3 phase 1 with a targeted completion in early 2027.
Ongoing monitoring and maintenance of shoreline restoration and native planting.
Continuing removal of invasive ironwood trees and mowing of undergrowth on RR3.
Development Update April 2026
Work continues at Kaihalulu East Drive with utilities being installed.
Most of the grading work on the mauka drainage basins has been completed.
Vertical construction at RR3 phase 1 to resume in April with a targeted completion in early 2027.
Phase 1 of shoreline restoration and native planting is complete with ongoing monitoring and maintenance in effect.
A huge mahalo to our golf maintenance team and Goodfellow Brothers (GBI) for clearing culverts and drainage pipes ahead of time to prevent major flooding.


